Big Bar landslide response information bulletin
February 28 2020
On this page
- Ongoing progress at the Big Bar landslide site
- Current images of work being done at the landslide site
Ongoing progress at the Big Bar landslide site
Following the initial blasting on the East Toe last week on February 18, crews have began preparing for a second blast, to occur in March.
Despite continued high winds, work has continued on several aspects of the project including:
- clean-up of debris from the initial blast;
- installation of additional mesh in high rock fall potential areas as identified by drone inspection;
- scaling work on the West face;
- final blasting on the overland access and hand scaling along the route;
- and archaeology work in preparation for additional excavation.
Current images of work being done at the landslide site