Big Bar landslide response information bulletin

February 28 2020

On this page

Ongoing progress at the Big Bar landslide site

Following the initial blasting on the East Toe last week on February 18, crews have began preparing for a second blast, to occur in March.

Despite continued high winds, work has continued on several aspects of the project including:

Current images of work being done at the landslide site

Picture of the landslide site
Initial blasting of the East Toe, which occurred last week. Click to enlarge.
Picture of the landslide site
Georadar monitoring equipment to measure slope grade and monitor slope movement. Click to enlarge.
Picture of the landslide site
Crews continue to scale the Overland Access. Click to enlarge.