Infographic: Big Bar landslide response - 2020 Timeline of key events
Release date: April 2021

Description: Big Bar landslide response - 2020 Timeline of key events
Abbreviations
- High Bar First Nation (HBFN)
- Stswecem’c Xgat’tem First Nation (SXFN)
- First Nations Leadership Panel (FNLP)
- Upper Fraser Fisheries Conservation Alliance (UFFCA)
- Province of British Columbia (Province)
- Public Service and Procurements Canada (PSPC)
- Fisheries and Oceans Canada (DFO)
- Peter Kiewit Sons ULC (Kiewit)
Winter
January 2020
- January 9: HBFN and SXFN met with PSPC, Kiewit and JESC to develop Indigenous Benefit Plan (IBP)
- January 13/14: Second contingency planning technical team meeting held
- January 14: Equipment mobilized to site; winter work commences
- January 17: DFO Minister Jordan met with HBFN and SXFN leadership, and Kiewit during site visit
- January 23: Tripartite After Action Review of Incident Command System and response held
February 2020
- February 18: First East Toe riverbank blast successfully completed, 1,200 m3 blast material removed
- February 21: Third contingency planning technical team meeting held
- February 27: HBFN, SXFN, Province and DFO visited site
- February 29: Site access completed
March 2020
- March 4: National and regional PSPC staff, alongside regional and local DFO staff, met with HBFN and SXFN on site
- March 9 -11: HBFN, SXFN and Upper Fraser Fisheries Conservation Alliance (UFFCA) review mitigation plans
- March 16: COVID-19 response launched across the Province, landslide response continues as part of emergency operations
- March 28: “Nature-like” fishway completed
- March 29: River in-channel blasting completed
Spring
April 2020
- April 11: Final East Toe riverbank blast completed, 1,800 m3 blast material removed
- April 14: Whooshh™ Innovations Ltd awarded contract for pneumatic fish pump equipment by PSPC
May 2020
- May 7: Concrete lock block fish ladder completed
- May 19: First long-term planning technical meeting held
- May 27: First day of DFO radio tagging operations
Summer
High water period: mid-June to early August
June 2020
- June 3: French Bar Creek Holding Facility for salmon operational
- June 3: Upper Fraser First Nations and DFO met to develop a process to identify and track priority Chinook stocks for emergency conservation enhancement
- June 8: First fish radio tagged
- Mid-June to early August: Sustained higher than average flow conditions delayed fish migration; Fish transport and enhancement operations interrupted due to flooding
- June 16: Second long-term planning technical meeting held
- June 20: First fish wheel operational downstream of Big Bar, led by Gitxsan Watershed Authorities in collaboration with St’at’imc Eco Resources and administered by the Fraser Salmon Management Council
- June 21: First two Chinook arrived at concrete fish ladder and transported to French Bar Creek Holding Facility
- June 21: Two-lane Whooshh Passage Portal™ operational
- June 23: First Chinook transported to Vanderhoof adult Chinook holding facility
July 2020
- July 2-3: Permanent fishway option endorsed by JESC and FNLP
- July 14: Initial salmon observed migrating upstream when water levels dropped to 4,000 m3/s
- July 18: Indigenous crews commence truck and transport operations
- July 17: Six-lane Whooshh™ system operational
- July 22: DFO monitoring team commences beach seining in Lillooet, BC
- July 23: First two salmon arrive at Churn Creek Hydroacoustic site, confirming fish passage upstream
- July 24: First fish transported through the Whooshh™ system
- July 25: First sockeye observed in concrete fish ladder
- July 31: First batch of sockeye transferred from French Bar Creek Holding Facility to Cultus Lake Salmon Research Laboratory (CLL)
August 2020
- August 4: Sockeye start arriving at Big Bar in greater numbers
- August 11: First spawning of 35 female sockeye at CLL
- August 12: Truck and transport operations suspended, 1,500 fish moved over the slide
- August 14: Target of collecting and transporting 400 Early Stuart sockeye to CLL achieved
- August 18: Last Chinook at French Bar Creek Holding Facility transported to Vanderhoof
- August 28: Whooshh™ tube extension completed and operational; French Bar Creek Holding Facility demobilization commences
- August 30: UFFCA commences natal stream brood collection
September 2020
- September 1: Third long-term planning technical meeting held
- September 8: Whooshh™ operations concluded, 8,200 fish moved through the system; Fish wheel operations began downstream for coho radio tagging
Fall
October 2020
- October 6: Indigenous partners and DFO released 20,000 2019 brood year Early Stuart sockeye as fall smolts
- October 21: DFO monitoring program concluded onsite operations and radio tagging activities, 1,000 fish radio tagged
- October 24: Alfalfa and Churn Creek sonars ceased operations, 161,000 fish detected 40 km upstream of slide site to date
November 2020
- November 17: PSPC awarded permanent fishway construction contract to Kiewit
December 2020
- December 7: JESC representatives briefed FNLP regarding next steps in permanent fishway implementation and 2021 summer operations
- December 8: HBFN and SXFN leadership visited the site along with DFO, PSPC, Provincial and Kiewit staff
- December 15: Fourth long-term planning technical meeting held
- Date modified: