Operational
Statement
Directional Drilling
Version 3.0 (PDF)
For the purpose of this Operational Statement, the term High-Pressure
Directional Drilling (HPDD) means trenchless methods of crossing
a watercourse using pressurized mud systems. HPDD is used to
install cables and pipelines for gas, telecommunications, fibre
optics, power, sewer, oil and water lines underneath watercourses
and roads. This method is preferable to open-cut and isolated
crossings since the cable or pipeline is drilled underneath
the watercourse with very little disturbance to the bed or banks.
HPDD involves drilling a pilot bore hole underneath the watercourse
towards a surface target, back-reaming the bore hole to the
drill rig while pulling the pipe along through the hole. This
process typically uses the freshwater gel mud system composed
of a mixture of clean, freshwater as the base, bentonite (clay-based
drilling lubricant) as the viscosifier and synthetic polymers.
One of the risks associated with HPDD is the escape of drilling
mud into the environment as a result of a spill, tunnel collapse
or the rupture of mud to the surface, commonly known as “frac-out”.
A frac-out is caused when excessive drilling pressure results
in drilling mud propagating toward the surface. The risk of
a frac-out can be reduced through proper geotechnical assessment
practices and drill planning and execution. The extent of a
frac-out can be limited by careful monitoring and having appropriate
equipment and response plans ready in the event that one occurs.
HPDD can also result in excessive disturbance of riparian vegetation
and sedimentation and erosion due to operation of equipment
on the shoreline or fording to access the opposite bank.
Fisheries and Oceans Canada (DFO) is responsible for protecting
fish and fish habitat across Canada. Under the Fisheries
Act no one may carry out a work or undertaking that will
cause the harmful alteration, disruption or destruction (HADD)
of fish habitat unless it has been authorized by DFO. By following
the conditions and measures set out below you will be in compliance
with subsection 35(1) of the Fisheries Act.
The purpose of this Operational Statement is to describe
the conditions under which it is applicable to your project
and the measures to incorporate into your project in order to
avoid negative impacts to fish habitat. You may proceed with
your high-pressure directional drill project without a DFO review
when you meet the following conditions:
- there is a low risk of frac-out, supported by a geo-technical
assessment,
- you have an emergency frac-out response plan and a contingency
crossing plan in place that outline the protocol to monitor,
contain and clean-up a potential frac-out and
- you incorporate the Measures to Protect Fish and
Fish Habitat when High-Pressure Directional Drilling
listed below in this Operational Statement.
If you cannot meet all of the conditions listed above and
cannot incorporate all of the measures listed below then your
project may result in a violation of subsection 35(1) of the
Fisheries Act and you could be subject to enforcement
action. In this case, you should contact the DFO office in your
area if you wish to obtain DFO’s opinion on the possible options
you should consider to avoid contravention of the Fisheries
Act.
You are required to comply with all municipal, provincial,
territorial and/or federal legislation that applies to the work
being carried out in relation to this Operational Statement.
In British Columbia, please contact the
Water Stewardship Division, Ministry of Environment for
information on the Provincial Water Regulation notification
requirements when planning to conduct high pressure directional
drilling in or around BC waters.
The activities undertaken in this Operational Statement must
also comply with the
Species at Risk Act. For general information on
aquatic SARA species visit the following web site:
http://www.dfo-mpo.gc.ca/species-especes/regions/Pac/pacific-index-eng.htm
and/or contact DFO by email at:
SARA@pac.dfo-mpo.gc.ca.
If you have questions regarding this Operational Statement,
please refer to the list of Frequently
Asked Questions or contact DFO Regional Headquarters at
1-866-845-6776.
Please notify DFO 10 working days before starting your work
by filling out and sending the
Pacific Region Operational
Statement notification form directly to DFO Regional Headquarters.
This information is requested in order to evaluate the effectiveness
of the work carried out in relation to this Operational Statement.
It is recommended that you keep a copy of the Operational Statement
at the work site to demonstrate to Habitat and Fishery Officer
staff that the conditions and measures, as outlined in the OS,
are being followed.
Area of Application
This Operational Statement applies to the province of British
Columbia and Yukon Territory freshwater systems only.
Measures to Protect Fish and Fish Habitat when High-Pressure
Directional Drilling
- Use existing trails, roads or cut lines wherever possible,
as access routes to avoid disturbance to the riparian vegetation.
- Design the drill path to an appropriate depth below
the watercourse to minimize the risk of frac-out and to
a depth to prevent the line from becoming exposed due to
natural scouring of the stream bed. The drill entry and
exit points are far enough from the banks of the watercourse
to have minimal impact on these areas.
- While this Operational Statement does not cover the
clearing of riparian vegetation, the removal of select plants
may be necessary to access the construction site. This removal
should be kept to a minimum and within the road or utility
right-of-way. When practicable, prune or top the vegetation
instead of uprooting.
- Machinery fording the watercourse to bring equipment
required for construction to the opposite side is limited
to a one-time event (over and back) and should occur only
if an existing crossing at another location is not available
or practical to use. A
Temporary
Ford Stream Crossings Operational Statement is also
available.
4.1. To exercise this option, the stream bed at the fording
site must be comprised of stable gravel or bedrock and the
stream banks must be low and stable.
4.2. If minor rutting is likely to occur, stream bank and
bed protection methods (e.g., swamp mats, pads) should be
used provided they do not constrict flows or block fish
passage.
4.3. Grading of the stream banks for the approaches is not
permitted.
4.4. If the stream bed and banks are steep and highly erodible
(e.g., dominated by organic materials and silts) and erosion
and degradation are likely to occur as a result of equipment
fording, then a temporary crossing structure or other practice
should be used to protect these areas.
4.5. Time the one-time fording to prevent disruption to
sensitive fish life stages by adhering to appropriate fisheries
timing windows.
4.6. Fording should occur under low flow conditions and
not when flows are elevated due to local rain events or
seasonal flooding.
- Operate machinery on land (above the
high water mark
(HWM)) and in a manner that minimizes disturbance to the
banks of the watercourse.
5.1. Machinery is to arrive on site in a clean, condition
and is to be maintained free of fluid leaks, invasive species
and noxious weeds.
5.2. Wash, refuel and service machinery and store fuel and
other materials for the machinery away from the water to
prevent any deleterious substance from entering the water.
5.3. Keep an emergency spill kit on site in case of fluid
leaks or spills from machinery.
5.4. Restore banks to original condition if any disturbance
occurs.
- Construct a dugout/settling basin at the drilling exit
site to contain drilling mud to prevent sediment and other
deleterious substances from entering the watercourse. If
this cannot be achieved, use silt fences or other effective
sediment and erosion control measures to prevent drilling
mud from entering the watercourse. Inspect these measures
regularly during the course of construction and make all
necessary repairs if any damage occurs.
6.1. Dispose of excess drilling mud, cuttings and other
waste materials at an adequately sized disposal facility
located away from the water to prevent it from entering
the watercourse.
- Install effective sediment and erosion control measures
before starting work to prevent entry of sediment into the
watercourse. Inspect them regularly during the course of
construction and make all necessary repairs if any damage
occurs.
- Monitor the fluid pressure or watercourse to observe
signs of surface migration (frac-out) of drilling mud during
all phases of construction.
Emergency Frac-out Response and Contingency Planning
- Keep all material and equipment needed to contain and
clean up drilling mud releases on site and readily accessible
in the event of a frac-out.
- Implement the frac-out response plan that includes measures
to stop work, contain the drilling mud and prevent its further
migration into the watercourse and notify all applicable
authorities, including the closest DFO office in the area.
Prioritize clean up activities relative to the risk of potential
harm and dispose of the drilling mud in a manner that prevents
reentry into the watercourse.
- Ensure clean up measures do not result in greater damage
to the banks and watercourse than from leaving the drilling
mud in place.
- In the event of a frac out, you will be required to
contact your local DFO
office for a review of an alternate crossing method.
- Stabilize any waste materials removed from the work
site to prevent them from entering the watercourse. This
could include covering spoil piles with biodegradable mats
or tarps or planting them with preferably native grass or
shrubs.
- Vegetate any disturbed areas by planting and seeding
with native trees, shrubs or grasses and cover such areas
with mulch to prevent erosion and to help seeds germinate.
All seeding and/or planting trees should follow the DFO
guidance on
Riparian Revegetation.
If there is insufficient time remaining in the growing season,
the site should be stabilized (e.g., cover exposed areas
with erosion control blankets to keep the soil in place
and prevent erosion) and vegetated the following spring.
6.1. Maintain effective sediment and erosion control measures
until revegetation of disturbed areas is achieved.