Infographic: Big Bar landslide timeline of key events
Release date: March 2020
Description: Big Bar landslide timeline of key events
Summer
- June 2019
- June 23 Slide reported to DFO
- June 28 Acoustic monitors installed
- June 29 Incident command post created in Lillooet, BC
- July 2019
- July 1 Local First Nations contacted and invited to collaborate as partners
- July 2 Joint Executive Steering Committee (JESC) created
- July 4 Rock scaling begins to provide safe working conditions at base of slide
- July 8 First Nations Leadership Panel created
- July 17 Radio tagging begins
- July 20 Beach seining and helicopter transport of fish begins
- July 22 Controlled blast to remove rock from wall for placement in river
- August 2019
- August 11 1st fish wheel operational
- August 16 High Bar & Canoe Creek First Nation archeological monitoring commences
- August 17 Fish transport road construction commence
- August 20 Initial salmon able to swim past slide via partly restored fish passage
- August 31 Rock scalers move large boulders to clear passage
- September 2019
- September 6 More than 140,000 salmon have swum past the slide
Fall
- October 2019
- October 1 Incident command response phase transitions to project management phase
- October 3-17 Winter site preparation work, including final Fisheries Act review for in-river blasting and construction work
- October 17 Demobilization of on-site equipment and crew complete, intensive planning process for winter work begins
- October 21 Big Bar Landslide JESC workshop to advance planning and procurement
- October 23 Fish radio tagging operations end
- November 2019
- November 27 Request for Information (RFI) posted by Public Services and Procurement Canada (PSPC)
- December 2019
- December 6 RFI closes
- December 8/9 Contingency planning technical team meeting
- December 10 Archeology work for overland site access begins
- December 18 PSPC tender period opens
- December 27 PSPC tender closes
Winter
- December 2019
- December 31 Peter Kiewit Sons ULC awarded contract for winter rock remediation by PSPC
- January 2020
- January 14 Equipment fully mobilized to slide, winter work commences
- January 23 Tripartite after action review of incident command phase
- January 9 High Bar and Stswecem’c Xgat’tem First Nation meet with PSPC, Kiewit & JESC to develop Indigenous Benefit Plan
- January 17 DFO Minister Jordan meets with HBFN & SXFN leadership and Kiewit for site visit